Load, Demand, Peak, and Load Factor

7 min · difficulty 3/10

Two feeders each move the same 2,880 MWh over a 30-day month. One serves an office park that runs nearly flat around the clock. The other serves a residential neighborhood that stays quiet all day and spikes hard from 5 to 9 p.m. Same energy delivered, same kilowatt-hours billed. Which feeder is using its wires better, and why would the utility care?

The flat feeder is, and the load hierarchy shows why. Instantaneous load is what a feeder draws at a single moment. Demand is that load averaged over a fixed interval, usually 15 minutes on a utility meter, never a one-second reading. Peak demand is the highest of those interval readings across the period. Load factor ties them together: it is average load divided by peak load over the same period, a unitless ratio that can never exceed 1 because the average can never sit above the peak.

Run the hook through it. Same 2,880 MWh over 720 hours means both feeders average 4 MW. The office park peaks near 4.5 MW, so its load factor is about 0.89. The residential feeder peaks at 10 MW to serve the same energy, so its load factor is 0.4. Identical energy, very different shapes.

Same average, different load factor Two 24-hour load curves plotted on the same 0 to 12 megawatt scale. The office park feeder is nearly flat, peaking at 4.5 megawatts around midday, with a gold dashed average line at 4 megawatts sitting close to its peak, labeled load factor 0.89. The residential feeder stays low overnight and spikes sharply from 5 to 9 p.m. to a peak of 10 megawatts, with the same 4 megawatt average line now sitting far below its peak, labeled load factor 0.40. Both curves average to the identical 4 megawatts. Same 4 MW average, two very different peaks Peak 4.5 MW Avg 4 MW 12 0 Office park feeder Load factor = 0.89 Peak 10 MW Avg 4 MW 12 0 Residential feeder Load factor = 0.40 Midnight Noon Midnight 24-hour load curve Load factor = average load ÷ peak load, same period. Same 4 MW average, but the flatter feeder needs far less installed capacity.
Load factor is average load divided by peak load. Same 4 MW average, but the flatter feeder needs far less installed capacity.

The reason a utility cares is that the transformer, the conductor, and the substation breaker are all sized to carry the peak, not the average. A low load factor means capacity was bought, installed, and energized that sits idle most hours of the month. The peaky residential feeder needed more than twice the equipment rating of the office park to deliver the exact same energy.

When you size a feeder transformer or read a customer’s demand profile, load factor tells you how hard the money on the pole is actually working. A flat load pattern delivers more energy per dollar of installed capacity than a peaky one. Just do not confuse load factor with the diversity, demand, and coincidence factors coming next lesson: those are different ratios that compare separate customers’ peaks against each other, not one feeder’s average against its own peak.

SAIDI and SAIFI targets drive capital planning, and capital planning drives what gets ordered and when. The Feeder tracks the reliability investment and regulatory signals behind those orders, free, every week.

Question 1 of 3

A feeder's average load over a 30-day month is 4 MW and its peak demand for that month is 10 MW. What is its load factor?

Educational material only. This is not engineering, safety, or procurement advice. Confirm any value against manufacturer documentation and a licensed professional before specifying equipment.