Data Center Load Pipeline vs Contracted: How to Discount It
Utility data center load pipeline vs contracted figures converted anywhere from 1.2:1 to 9:1 this quarter. Here is how to discount a large-load GW number.
Six utilities and one turbine manufacturer put large-load numbers on the record in the same earnings window, and no two of them counted the same way. The spread on data center load pipeline vs contracted conversion ran from roughly 1.2:1 to about 9:1 depending on whose disclosure you read. That is not a rounding difference. A distributor sizing inventory against a territory number, or a municipal utility deciding whether a 300 MW inquiry is real, is working from a figure that could be off by most of an order of magnitude in either direction.
The useful output of reading all of them together is not an average. It is that a large-load gigawatt figure quoted without its conversion tier is unusable, and that two utilities both saying “pipeline” are frequently not describing comparable objects.
The utility large load pipeline discount, six ways
Here is what the quarter actually disclosed.
PG&E reported a data center pipeline of 12.7 GW, up from 5.1 GW in Q1 2026, while telling investors it expects to serve roughly 1.8 GW of new data center load by 2030. That is about 7:1, published by the utility rather than inferred by an outside analyst. CEO Patti Poppe framed the screen directly: “As we continue to build our pipeline, we’re focusing not on size, but on quality.”
CenterPoint submitted more than 17 GW to ERCOT’s Batch Zero process and expects around 14 GW to qualify, roughly 1.2:1, with about $900M in customer cash commitments and deposits sitting behind the submissions.
DTE reported 2.4 GW of executed agreements against another 5 to 6 GW it describes as development pipeline, so somewhere between 3:1 and 3.5:1 depending on which end of its own range you take. The executed tier is almost entirely two named customers, which is rare disclosure: Oracle at 1.4 GW, approved and under construction with demand ramping in 2027 and 2028, and Google at 1 GW still before the Michigan Public Service Commission.
Xcel discloses in three explicitly labeled tiers: roughly 2 GW contracted or under construction now, roughly 4 GW contracted by end of 2027, and roughly 3 GW of incremental line of sight ramping into the mid-2030s. The middle tier carries a date, which makes it the most plannable disclosure in the set.
Exelon identifies 11 GW of high-probability load, split 9 GW at ComEd and 2 GW in the Mid-Atlantic. Of that, 4 GW is backed by signed, FERC-approved Transmission Security Agreements supported by about $1 billion in collateral. The other 7 GW predates the TSA process.
AEP publishes the largest number in the set and the one that looks cleanest on its face: 69 GW of contracted load growth through 2030, up 6 GW in the quarter from a 63 GW base. We will come back to that one, because it is not what it appears to be.
GE Vernova, on the equipment side of the same market, signed 20 GW of new gas equipment contracts in the quarter. Only 2 GW were actual orders. The other 18 GW were slot reservations, roughly 9:1, and the company converted 10 GW of previously held reservations into orders while shipping 3 GW.
AEP’s contracted data center load GW is really two numbers
AEP’s 69 GW is the most instructive disclosure of the quarter, and the instruction is buried in a qualifier.
On the earnings call, CFO Trevor Mihalik described the figure as 69 GW of contracted load additions through 2030 “all supported by a combination of fully executed ESAs and LOAs.” Those are two different instruments. An electric service agreement is a service contract. A letter of agreement is a commitment to proceed toward one.
The split matters because Mihalik also disclosed that 45 GW of the 69 sits in AEP Texas and is supported by fully executed LOAs. Meanwhile CEO Bill Fehrman attached the company’s headline customer-benefit claim specifically to the other instrument, projecting fixed cost offsets for residential customers of up to $16 billion at its vertically integrated utilities “supported by fully executed take-or-pay electric service agreements.” Those vertically integrated utilities are not in Texas.
So the single largest contracted figure any US utility published this quarter contains its own two-tier structure, and the take-or-pay terms that make contracted load meaningful for equipment buyers attach to the smaller of the two tiers. That is not a criticism of the disclosure. AEP said exactly what it did, in public, on the record. It is a warning about what happens two hops downstream, where “69 GW contracted, backed by take-or-pay” becomes a single sentence in a trade summary and then a planning input in somebody’s territory model.
Read the qualifier. It is almost always there, and it is almost always dropped first.
Collateral is the only tier that cannot be walked back for free
Announcements are free. Letters of agreement are cheap. Collateral is not, which is why it is the sharpest tool available for reading data center load pipeline vs contracted claims.
A developer that has posted cash against a FERC-approved agreement has converted a press release into a balance-sheet position, and that is the point in the chain where substation transformers, breakers and feeder scope actually get specified and ordered. Everything upstream of it is an option.
Two utilities now publish the collateral directly, and comparing them is worth doing. Exelon reports about $1 billion behind 4 GW. AEP reports collecting nearly $2 billion in cash or collateral in a single month, covering all required credit support for the full 45 GW in its Texas Batch Zero filing. Divide those out and the per-kilowatt commitment behind Exelon’s TSA tier is roughly five times what sits behind AEP’s Texas tier.
Neither utility is wrong. They are running different instruments under different regulators, and ERCOT’s Batch Zero credit requirement is calibrated to a different risk than PJM-region transmission security. That is the point. Even collateral-backed load, the strictest tier available, is not one uniform thing across territories. The deposit structures themselves are contested and moving, as the ERCOT interconnection pause and its deposit terms demonstrated three weeks later when a governor froze the queue mid-cycle with hundreds of millions already posted.
The instrument decides who buys the substation
This is where the exercise stops being media criticism and starts paying for itself.
A take-or-pay electric service agreement obligates the large load to pay whether or not it consumes. That structure is what pushes the cost of the grid infrastructure serving an interconnection onto the customer being served, which means the equipment spend lands on that customer’s project, on that customer’s schedule, funded by that customer. Without it, the same equipment lands in rate base, on the utility’s schedule, at the utility’s pace.
For a municipal utility or cooperative negotiating its first large-load interconnection, that distinction is the whole negotiation. AEP’s structure is the most concrete public template available for making the load fund its own infrastructure, and it is described in enough detail in an earnings release to bring to a board meeting. The cost-allocation approach Pennsylvania took with its large load tariff is the regulatory counterpart, and the equipment scope that follows from a data center substation design decision is where the money actually goes.
DTE supplies the sharpest example of what a schedule commitment is worth. The company has publicly said it plans to refrain from filing another electric rate request until at least 2028, contingent on the Oracle project coming online as planned. That converts one customer’s interconnection schedule into a regulatory promise with a named date. Every long-lead item on that project now sits on the critical path of an affordability commitment rather than a construction plan, which tells you something about how hard that utility will work to hold a delivery slot.
How to read utility capex and data center load claims: four questions
The checklist is short enough to apply to the next press release without us.
One. Which tier is this? Executed, contracted, in negotiation, or inquiry. If the release does not say, the number is a pipeline figure regardless of the word attached to it.
Two. Is there a named instrument, and what does it obligate? Take-or-pay ESA, letter of agreement, transmission security agreement, or nothing. Ask whether the obligation survives the customer changing its mind.
Three. What did the project have to post to be counted? This is the single best predictor of large load interconnection conversion rate. A deposit-gated queue converts near unity. A free queue converts somewhere between one in five and one in ten, because a developer files in five territories to hold optionality and builds in one.
Four. Did the number move, and did the utility explain the move? DTE’s $30 billion capital plan was flat quarter over quarter, which reads as restraint until you notice the prior plan was $24 billion over 2025 to 2029. The plan rose 22% one quarter earlier, attributed primarily to a single data center customer. Flat since the increase is a different claim from flat.
Run those four against any utility disclosure and the data center load pipeline vs contracted gap stops being a mystery and becomes a number you can plan against. Skip them and you inherit whoever summarized it first. We applied the same discipline to three utilities’ hyperscaler capex strategies in Q1, and the pattern held then too.
The open term nobody has priced yet
One thing is missing from every one of these agreements, and it has a deadline.
FERC ordered NERC on July 16, 2026, in Docket RD26-7-000, to file mandatory reliability standards governing the integration of computational loads by December 31, 2026, along with registry criteria that would bring large computational-load entities directly under the mandatory reliability framework. Phase II work is due March 1, 2027. The Commission cited a July 2024 Eastern Interconnection event in which roughly 1,500 MW of data center load was lost, and facilities capable of dropping between 17% and 95% of consumption within milliseconds of a transmission fault.
Registration is what makes a NERC standard enforceable, with civil penalty exposure attached. Once those criteria land, a large computational load above the threshold becomes a registered entity in its own right rather than a customer of one. None of the public reporting on the agreements signed this quarter says who carries the registration and compliance obligation at the point of interconnection, and most of these contracts were drafted when the load could not be a registered entity at all.
That is a real open contract term with a known closing date. A cooperative or municipal utility courting large load should be asking now, while the criteria are still out for comment, whether its interconnection agreement allocates reliability-compliance responsibility to anyone. The broader FERC large load interconnection rulemaking is the other half of the same clock.
Large-load disclosures move every quarter and the qualifiers move with them. The Feeder is our free monthly briefing on what changed in the filings and what it means for equipment timing. Sign up here.
Related Reading
- ERCOT Data Center Interconnection Pause: The Deposit Trap
- Hyperscaler Utility Capex 2026: Three Q1 Strategies
- Data Center Substation Design Is a Procurement Decision
Frequently Asked Questions
What is the difference between data center load pipeline vs contracted figures?
A pipeline figure counts every large-load project that has approached the utility, including projects that have posted nothing and signed nothing. A contracted figure counts only projects under an executed agreement. In Q2 2026 disclosures the gap between the two ran from about 1.2:1 at CenterPoint to about 7:1 at PG&E, so the two words describe objects that differ by most of an order of magnitude.
How much should I discount a utility's announced data center GW number?
There is no defensible industry-wide discount factor. Ask instead what a project had to post to be counted. A queue with a cash deposit or collateral requirement converts close to unity. A queue that is free to enter converts at somewhere between one in five and one in ten.
Does contracted load mean the customer pays for the substation?
Only if the contract says so. A take-or-pay electric service agreement obligates the large load to pay whether or not it consumes, which is what pushes the substation and switchgear spend onto that customer's project. A letter of agreement or a non-firm arrangement leaves the spend in rate base on the utility's schedule.
Free RFQ templates. Weekly digest. Yours.
Free Member tier. Pick your topics. Get a weekly digest filtered to what you actually buy.