Price is one criterion in a scored utility RFP, and some solicitations say exactly how much it counts. When Tacoma Power went out for single-phase pad-mounted distribution transformers in 2026, its published scoring table gave pricing 20 points out of 100. The other 80 went to order planning, emergency response, unit markings, supply chain reliability, past performance, specification exceptions, sustainability and DOE 2029 readiness.

Those are the sections a bidder can win or lose without touching price. This guide walks through how utility RFP evaluation actually works, using three solicitation documents a bidder can open and read: a public-power equipment RFP with its full rubric, a public-power procurement policy that defines the contest types and the protest path, and an investor-owned utility rubric with hard Go/No-Go gates. Each is one utility’s document. None of them is a national rule, and the first thing a good response does is read the one in front of it.

First, Know Which Contest You Are In

Before scoring, there is classification. The word “RFP” gets used loosely, but a utility’s own procurement policy usually defines several different sourcing events, and they reward different things.

Colorado Springs Utilities, a community-owned utility, spells this out in its procurement policy (Version 25, approved April 1, 2026):

  • Request for Proposal (RFP): award goes to the response “deemed to be most advantageous, including from negotiations, in terms of criteria designated, combining both technical and cost considerations.”
  • Request for Quotation (RFQ): written quotes for price and delivery meeting minimum requirements, with award to the “lowest Responsive and Responsible Bidder.”
  • Invitation for Bid (IFB): non-negotiable, unless only one quotation is received, with award to the lowest responsive and responsible bid.

The practical consequence for an electric utility RFP response: in an RFQ or IFB, your job is to be responsive, responsible and cheapest. In an RFP, you are being scored on a rubric, and a lower price can lose to a stronger technical answer. Writing an RFQ-style response (a price sheet and a spec sheet) to a criteria-scored RFP leaves most of the points on the table.

A Real Utility RFP Scoring Table

Tacoma Power/Transmission & Distribution’s RFP PT26-0030F, for single-phase pad-mounted distribution transformers (submittals due April 7, 2026), publishes the whole rubric. The RFP says a Selection Advisory Committee will evaluate submittals against this table:

Criteria (Tacoma Power, PT26-0030F)Max points
Material requirements planning program20
Pricing20
Prior contracts / product performance15
Data submissions / unit markings10
Supply chain reliability10
Technical specification exceptions10
Emergency response5
Sustainability5
Amorphous core project (DOE 2029 readiness)5
Contract exceptions0
Total100

Read the table as a list of what this buyer was worried about. Order planning ties with price for the top slot. Past performance on installed units outweighs sustainability three to one. And the solicitation says the committee may interview the most qualified respondents and rescore submittals afterward.

Utility RFP Evaluation Criteria: What the Other 80 Points Asked For

The Tacoma document is useful because each criterion comes with a prompt, and the prompts show what a strong answer contains.

Order planning (20 points). The RFP asks for the bidder’s preferred planning method, allocation-based or as-needed, with detailed timelines. Its own example: allocation requests received by August, confirmations by mid-September, orders for the coming year placed by late October. A response that says “we will work with you on scheduling” scores against that example, not against nothing.

Prior contracts and product performance (15 points). References must be US utility customers with contract contacts, and the RFP says those references should have units installed and performing for at least ten years. A new product line will struggle to answer this with a brochure.

Supply chain reliability (10 points). The prompt asks what the bidder changed after the pandemic and under current tariffs, and states that preference will be given to companies using North American products such as metals and components. Pair this answer with your domestic-content documentation; our BABA compliance guide for transformer procurement covers what that paperwork looks like.

DOE 2029 readiness (5 points). Bidders describe how they will comply with the 2029 federal efficiency requirements, when compliant units ship, and how they will help customers update accepted drawings. The DOE 2029 transformer efficiency guide covers the rule itself.

Pricing (20 points). The prompt asks bidders to disclose the public or proprietary index used to calculate pricing and states a preference to award to the lowest priced response. Price still matters. It is simply one line of ten.

Exceptions (10 points, and 0). Technical specification exceptions carry 10 points. Contract exceptions carry none, but that does not make them free: see the gate below.

Gates Come Before Points

Scoring only applies to submittals that clear the gates, and gates are where good bids die quietly.

Tacoma’s RFP states that “a significant deficiency in any one criteria is grounds for rejection of the submittal as a whole,” and that submittals which are incomplete, conditioned, or contain alternatives not called for may be rejected as non-responsive. It also caps page count and says pages over the limit will not be evaluated.

Investor-owned utilities can build gates into the rubric itself. Rhode Island Energy, part of the PPL Corporation family, published this evaluation rubric for a non-wires solution RFP (Staples #112, Rev 1, June 17, 2024):

Criteria (Rhode Island Energy NWS RFP)Weight
Cost: total project cost at or below the best utility reliability solutionGo/No-Go
Cost-effective (benefit-cost framework)25; No-Go if BCR below 1.0
Reliable25; No-Go if deemed not reliable
Prudent25; No-Go if deemed not prudent
Environmentally responsible25; No-Go if not environmentally responsible

The criteria come from Rhode Island’s Least-Cost Procurement Standards, and each evaluation committee member scores every proposal on the same rubric before scores are averaged. Keep the scope honest: this is a regulator-framed non-wires solicitation, not an equipment purchase, and it does not show how any investor-owned utility scores a transformer or switchgear bid. What it does show is a pattern worth checking in every solicitation: a proposal can score well on three criteria and still be out on the fourth.

After Scoring: Intent to Award and Protests

Scoring ends in an award decision, and public utilities often publish a formal path from there. Colorado Springs Utilities requires a written Intent to Award for all formal sourcing events. A contract awarded under a formal sourcing event cannot be executed for at least three business days after that notice is published. The policy says the wait avoids entering into a contract that could be protested, and a protest of the award procedure must reach the Procurement Manager no later than three business days after the notice, unless the supplier first requests additional information.

That is one utility’s timetable. Protest windows, who may file, and what triggers the clock differ between utilities and between solicitation types, so the only safe deadline is the one in the governing policy. At Colorado Springs Utilities the clock runs from publication of the Intent to Award, so a bidder who is not watching for that notice can lose the window without knowing it opened.

Where Utility RFPs Are Posted

Discovery is utility by utility. Colorado Springs Utilities posts new solicitations through SOVRA BidNet and asks suppliers to register there. Tacoma posts formal bids on the city’s purchasing pages, which is where PT26-0030F lives.

The dependable approach is to identify the utilities in your territory, find each one’s supplier or purchasing page, and register on the portal that page names.

A Utility RFP Response Checklist

This is an editorial checklist built from the documents above. It is not any utility’s scoring sheet.

  1. Classify the event. RFP, RFQ or IFB, as defined in that utility’s own policy. Match the response to the contest.
  2. Map every criterion to a section. Answer in the order the solicitation lists, and do not cross-reference; Tacoma asks for each answer in a single location.
  3. Answer the example, not the heading. Where the solicitation gives an example timeline or format, respond to it directly.
  4. Clear every gate first. Page limits, required forms, completeness, and anything marked No-Go or grounds for rejection.
  5. Budget effort by points. A criterion worth 20 points deserves more pages and evidence than one worth 5.
  6. Keep exceptions minimal and explicit. List specification exceptions where asked; treat contract exceptions as a responsiveness risk even at zero points.
  7. Bring references that fit the ask. Utility customers, named contacts, and installed units old enough to meet the stated minimum.
  8. Calendar the award notice. Know the protest window before you submit.

Utility buyers writing their own solicitation can work from the other side: the free transformer RFQ builder produces a draft and an engineering review checklist, and the transformer bid evaluation guide covers weighing responses when lead times run long.

Stay Ahead of the Next Solicitation

The Feeder is our free weekly read on the procurement, supply and regulatory signals that move utility and grid equipment demand, written for the people who place and answer the orders. Subscribe to The Feeder.

Frequently Asked Questions

How are utility RFPs evaluated?

It depends on the utility and the solicitation type, and the scoring method is usually printed in the solicitation itself. Tacoma Power's 2026 RFP for single-phase pad-mounted distribution transformers, for example, set out a 100-point table for its Selection Advisory Committee to evaluate submittals, in which pricing carried 20 points and the rest went to order planning, emergency response, supply chain reliability, past performance, unit markings, specification exceptions, sustainability and DOE 2029 readiness.

What is the difference between an RFP, an RFQ and an IFB at a utility?

Colorado Springs Utilities' procurement policy (Version 25, approved April 1, 2026) defines an RFP award as the response 'deemed to be most advantageous' on designated criteria 'combining both technical and cost considerations'. An RFQ or an IFB is awarded to the lowest responsive and responsible bidder. Other utilities use their own definitions, so read the one in the solicitation you are answering.

Can a bidder protest a utility contract award?

Check the governing procurement policy. Colorado Springs Utilities, for example, publishes an Intent to Award for formal sourcing events and will not execute the contract for at least three business days after that notice, and a protest of the award procedure generally must be received within three business days of it. Timing and eligibility are set utility by utility, so check the policy that governs the solicitation.