September 9, 2026 8 min read Virginia Makes Data Centers Pay for Their Own Substations Virginia's SCC ordered a mandatory CIAC so large loads fund the substations built to serve them. What Case PUR-2026-00056 changes for equipment buyers. virginiadominiondata-centers Read Analysis DistroForge Research
September 8, 2026 9 min read Pennsylvania Data Center Executive Order 2026-05 Decoded Pennsylvania data center executive order 2026-05 closes the permit fast lane and names both PJM cost dockets. The procurement read for equipment buyers. pennsylvaniadata-centerslarge-load Read Analysis DistroForge Research
September 3, 2026 7 min read FERC MISO Tranche 2.1 Cost Recovery PJM: No Bid Required FERC approved MISO Tranche 2.1 cost recovery for PJM-side facilities in docket ER26-1538. Five named utilities build the work, with no competitive solicitation. FERCMISOPJM Read Analysis DistroForge Research
September 2, 2026 8 min read TVA Data Center Rate Lands Oct 1 on 153 Distributors The TVA data center rate takes effect October 1 above 153 municipal and cooperative distributors that deliver 99% of the load it prices. TVAlarge load tariffdata centers Read Analysis DistroForge Research
August 31, 2026 8 min read CAISO Large Load Requirements: A PMU at Every Transformer CAISO large load requirements leave rates alone and add a PMU, DFR and SCADA at every main power transformer. Comments close September 2. CAISOlarge loaddata centers Read Analysis DistroForge Research
August 30, 2026 6 min read The First Data Center Utility Contract Disclosure Is Due Georgia Power owes the PSC a public summary of its 3,200 MW OpenAI contract. The first data center utility contract disclosure tests what load is real. data centerslarge loadregulatory Read Analysis DistroForge Research
August 27, 2026 10 min read Grid Equipment Executive Order: Read the 69 kV Line First Executive Order 14421 bars some foreign grid equipment transactions. Its bulk-power definition excludes local distribution. What is actually in scope. executive orderEO 14421bulk power system Read Analysis DistroForge Research
August 24, 2026 7 min read Wildfire Mitigation Federal Land Permitting: 1 in 3 Late Wildfire mitigation federal land permitting misses its own 120-day target on nearly a third of Forest Service requests. What that does to a pole order. wildfire mitigationfederal land permittingvegetation management Read Analysis DistroForge Research
August 21, 2026 8 min read USDA Will Forgive 40% of These Rural Utility Loans. The Match Cannot Be Borrowed. The USDA rural utility loan program 2026 forgives up to 40% of a loan. Letters of interest are rolling from September 8, and the match cannot be debt. USDARUScooperatives Read Analysis DistroForge Research
August 11, 2026 10 min read ERCOT Data Center Interconnection Pause: The Deposit Trap The ERCOT data center interconnection pause froze Batch Zero with hundreds of millions in deposits posted. ERCOT now says the study slips past April 2027. ERCOTTexasdata centers Read Analysis DistroForge Research
August 8, 2026 7 min read Large Load Resource Adequacy: What Six RTOs Told FERC All six grid operators filed large load resource adequacy reports on July 20. ISO-NE wants data centers to bring their own generation. Here is what each one answered. FERCdata centerslarge load Read Analysis DistroForge Research
August 7, 2026 7 min read Section 202(c) Must-Run Orders Defer Seven Retirements Seven plants sit under rolling Section 202(c) must-run orders deferring retirement. The renewal dates are public, and the first one falls August 16. Section 202(c)DOE emergency ordermust-run Read Analysis DistroForge Research